Title of Invention

SLURRY BUBBLE COLUMN REACTOR.

Abstract A slurry bubble column reactor comprising a slurry zone arranged to contain in use a volume of slurry comprising a liquid phase in which solid particles are suspended, a gas space above the slurry zone, gas supply apparatus (11) arranged to supply gas to the slurry zone, a gas outlet from the gas space, and a liquid outlet The gas supply apparatus (11) comprises a gas supply pipe (13), gas manifolds (14) tubular distribution rings (20-24) and a set of gas nozzles (40) The nozzles (40) open downwards and are arranged in use to inject gas into the slurry zone of the reactor (11), thereby forming downwardly extending gas jets of length L in the slurry The nozzles (40) are distributed generally evenly across the cross section of the reactor (11) and are arranged to direct their gas jets towards the bottom of the reactor (11), in order to dislodge settling catalyst particles.
Full Text 2 Slurry Bubble Column Reactor
The present invention relates to a gas distributor arrangement in a three phase reactor or slurry bubble column reactor (SBCR)
SBCRs are employed to conduct many chemical reactions, particularly reactions in which the reactants are gaseous, the products include liquids, and a solid catalyst is required In such a reaction, the gaseous reactants are introduced into a slurry of finely divided catalyst in a liquid medium which may contain a liquid reaction product The gas introduction is achieved using a gas distributor
A gas distributor for a slurry bubble column should satisfy some important requirements, which include
• the gas should be distributed evenly over the entire reactor cross sectional area,
• the catalyst particles should be well dispersed,
• stagnant zones, especially at the bottom of the reaction, must be avoided,
• penetration of catalyst particles into the gas distributor during planned or unplanned
reactor shutdowns must be minimised,
• erosion of reactor walls and internals should be avoided,
• the distributor should not induce unacceptable attrition of the catalyst, and
• the pressure drop should be low, for economic reasons
The present invention was made with those objectives in mind
There are several references teaching means for distributing and injecting synthesis gas into a slurry bubble column in Fischer-Tropsch processes So far no reference has been identified that teaches the features of the present invention, for instance the geometric requirements pertaining to the nozzles
Two fundamentally different solutions for the distribution of gas into a fluidised bed or a slurry reactor exist, a one-stage system and a two-stage system

3
In a two-stage system, the gas first is introduced to the reactor through a injection device into
a plenum chamber, and thereafter the gas is distnbuted,through a gas distribution plate which covers the entire cross sectional are of the reactor
In a one-stage system only one gas sparger is used, and the gas is injected into the reactor through an arrangement of feed nozzles which covers parts of the leactor cross sectional area In reactors with internals, such as heat exchangers, a one-stage system with a pipe grid or a sparger in most cases is sufficient Downward pointing nozzles prevent clogging of the sparger with catalyst particles if the gas flow is stopped and are more effective for redispersing the catalyst In addition, downward gas ejection gives somewhat better bubble formation than upward ejection
US-A-2001/0018462 discloses a gas distribution grid which includes a set of upwardly pointing gas injectors which protrude from the bottom of the reactor The throat and cone gas injector here is clearly an example of a two-stage system
In US-A-2853369, gas inlet nozzles are shown which can be dnected downwardly towards the bottom of the reactor Two alternative configurations of gas distribution pipes are shown
US-A-5620670 states that a uniform distribution of synthesis gas fed uniformly to across the reactor cross section is necessary to achieve good mixing between the rising gas bubbles and the slurry medium containing the dispersed catalyst particles The gas distributor may consist of orifices or porous metal spargers A preferred design using orifices consists of concentric rings or torroidal manifolds nested in such a manner that the rings follow the contour of the bottom head of the reactor, with the largest diameter ring at the highest elevation and the smallest ring at the lowest elevation The orifices can be placed facing upwards or downwards or both
US-A-4443551 describes a distributor for delivering high velocity gas from a gas distributor through a nozzle with decreased erosion in the nozzle Its primary use is as a distributor for oxygen-containing gas for use in the regeneration of spent catalyst used in fluid catalytic cracking processes Lance type distributors may be used as well as nozzles pointing

4
downwards at 30-75° The gas distributors can have the shape of tubular rings that may be
positioned at different horizontal levels
According to one aspect of the invention, there is provided a slurry bubble column reactor comprising a slurry zone arranged to contain in use a volume of slurry comprising a liquid phase in which solid particles are suspended, a gas space above the slurry zone, gas supply apparatus arranged to supply gas to the slurry zone, a gas outlet from the gas space, and a liquid outlet, the gas supply apparatus comprising gas supply and distribution means and a set of gas nozzles, the gas supply and distribution means being arranged to deliver the gas to the set of gas nozzles, the nozzles opening downwards and being arranged in use to inject gas into the slurry zone of the reactor, thereby forming downwardly extending gas jets of length L in the slurry, the number and the configuration of the nozzles being selected to provide a distribution of nozzles across a cross section of the reactor which corresponds to a minimum density of 75 evenly distributed nozzles per m2 the opening of each nozzle being positioned a perpendicular distance D from the surface of the bottom of the reactor, wherein D = 0 75 to 1 5L
In this way, any catalyst particles with a tendency to settle at the bottom of the reactor are dislodged and kept in motion by the gas jets and the downwards pointing nozzles prevent clogging of the gas-distributor if the flow is stopped
Preferably, the gas supply and distribution means comprise a gas supply means and a separate gas distribution means, and these are preferably tubular Preferably, the tubular gas supply means is connected to one or more gas supply inlets and also to a plurality of tubular gas distribution means, along which the nozzles are arranged
To avoid differences in radial distribution of gas, the nozzle pressure drop should preferably be sufficiently large compared to the dynamic pressure in the gas distributor pipes, I e there must be a minimum pipe diameter in order to avoid radial maldistribution The gas distributor pipe cross sectional area should preferably be at least twice the sum of nozzle areas in the pipe

5
In a preferred embodiment, the tubular gas supply means comprises two or more tubular
structures extending radially from one gas supply inlet located centrally with respect to the general geometry of the reactor, and in which the tubular gas distribution means are mounted generally perpendicular to the respective axes of the tubular structures comprising the gas supply means to which each tubular gas distribution means is connected The distribution means may be in the shape of concentric rings or tubular toroids, or sections thereof, or in the shape of curved tubes, the centre line of each such tube lying in a respective vertical plane and may take the form of a pipe grid which is part spherical in shape
Preferably, the dimension L is from 5 to 20 cm, more preferably 10 to 15 cm Preferably, the diameter of the openings of the gas nozzles is equal to or greater than 5 mm, and may be less than 12 mm, preferably from 6 to 10 mm
Preferably, the openings of the nozzles are arranged so that the principal axis of the jets of gas produced has an inclination of 45° or less to the vertical Preferably, the distribution of nozzles with respect to a horizontal plane is such that it provides at least 75 nozzles in any arbitrarily situated circular area of 1 m2
Preferably, the bottom of the reactor has a curved or part-spherical shape and the gas distribution means generally conforms to this shape Preferably, the openings of the nozzles he on a virtual surface which conforms to this shape Preferably, the openings of at least 95% of the nozzles are equidistant from the bottom of the reactor Preferably, the openings of the nozzles are configured to direct the jet of gas perpendicularly towards the surface of the bottom of the reactor, when the reactor is in use The nozzles may be constituted by orifices formed through the wall of the distribution means A gas distributor pipe-grid with a hemispherical shape, is therefore preferred, located with a distance between the nozzle outlets and the bottom of the reactor close to the length of the gas jet out of the nozzles If the distance between the nozzle outlet and the bottom of the reactor is significantly larger than the length of the gas jets out of the nozzles, a layer of catalyst particles will build up at the bottom of the reactor, since the liquid movement below the gas jets would be low (The length of the gas jet out of each nozzle would typically be less than 20 cm) If the distance between the nozzle outlet and the bottom of the reactor is significantly less than the length of the gas jet, erosion of the bottom of the reactor under the nozzles might be a severe problem

6
With a flat gas-distributor, the distance between the nozzles and the bottom of the reactor will
vary The result can be erosion problems in some parts of the bottom of the reactor, while build-up of catalyst particles can be a problem in other parts
With a hemispherical shape of the gas distributor pipe grid, the distance between each of the nozzles and the bottom of the reactor can be constant
With an increasing gas velocity out of the nozzles, 1 e an increasing energy content, the attrition of catalyst particles also increases The gas velocity should therefore be as low as possible, but sufficiently high to give a nozzle pressure drop high enough to avoid axial maldistribution of gas
Experiments have shown that below the gas jets, the liquid circulation was low Therefore, in order to avoid stagnant zones at the bottom of the reactor, and at the same time minimise erosion at the bottom of the reactor, the distance between the nozzle outlets and the bottom of the reactor should be in the same range as the estimated jet length If the bottom of the reactor has a hemi-sphencal shape, the gas distributor should also have the same hemispherical shape in order to achieve the same distance between the nozzle outlets and the bottom of the reactor over the entire reactor cross sectional area
The invention also extends to a method of conducting a chemical reaction involving gaseous reactants which comprises supplying the gaseous reactants to a reactor as described above, by way of the gas supply apparatus, in which method, the reactoi contains a volume of slurry comprising a liquid phase and solid catalyst particles, and the catalyst particles are maintained in suspension in the slurry by rising gas bubbles from the gas supply apparatus
Preferably, the gas flowing through each individual nozzle exerts a dynamic pressure of less than 15 000 kg/m s2, more preferably less than 10,000 kg/ms2, for example a pressure in the range 5,000 to 8,000 kg/ms2 With a hemispherical pipe-grid shape, there will be differences in the hydrostatic pressure for the nozzles To avoid differences in axial distribution of gas due to differences in hydrostatic pressure, preferably, the hydrostatic pressure difference between the highest and the lowest located nozzles in the reactor is less than 10 times the

7
pressure drop across an individual nozzle Preferably, the length L and the distance D satisfy
the equation D = 0 8 to 1 4L, most preferably D = 0 9 to 1 2L
The method may be applied to a Fischer-Tropsch synthesis reaction, for example, one in which the reaction temperature is in the range 150 to 300°C, the reaction temperature is in the range 175 to 250°C, and the reaction pressure is in the range 1 to 100 bar Preferably, the temperature is in the range 200 to 235°C and the pressure is preferably in the range 15 to 25 bar
According to a second aspect of the invention, there is provided a slurry bubble column reactor comprising a slurry zone arranged to contain in use a volume of slurry comprising a liquid phase in which solid particles are suspended, a gas space above the slurry zone, gas supply apparatus arranged to supply gas to the slurry zone, a gas outlet from the gas space, and a liquid outlet, the gas supply apparatus comprising gas supply and distribution means and a set of gas nozzles, the gas supply and distribution means being arranged to deliver the gas to the set of gas nozzles, the nozzles opening downwards and being arranged in use to inject gas into the slurry zone of the reactor, thereby forming downwardly extending gas jets of length L in the slurry, the nozzles being distributed generally evenly across the cross section of the reactor and being arranged to direct their gas jets towards the bottom of the reactor, in order to dislodge settling catalyst particles
According to a third aspect of the invention, there is provided a slurry bubble column reactor comprising a slurry zone arranged to contain in use a volume of slurry comprising a liquid phase in which solid particles are suspended, a gas space above the slurry zone, gas supply apparatus arranged to supply gas to the slurry zone, a gas outlet from the gas space, and a liquid outlet, the gas supply apparatus comprising gas supply and distribution means and a set of gas nozzles, the gas supply and distribution means being arranged to deliver the gas to the set of gas nozzles, the nozzles opening downwards and being arranged in use to inject gas into the slurry zone of the reactor, thereby forming downwardly extending gas jets of length L in the slurry, the number and the configuration of the nozzles being selected to provide a distribution of nozzles across a cross section of the reactor which corresponds to a minimum density of 75 evenly distributed nozzles per m2

8
According to a fourth aspect of the invention, there is provided a slurry bubble column
reactor comprising a slurry zone arranged to contain in use a volume of slurry comprising a liquid phase in which solid particles are suspended, a gas space above the slurry zone, gas supply apparatus arranged to supply gas to the slurry zone, a gas outlet from the gas space, and a liquid outlet, the gas supply apparatus comprising gas supply and distribution means and a set of gas nozzles, the gas supply and distribution means being arranged to deliver the gas to the set of gas nozzles, the nozzles opening downwards and being arranged in use to inject gas into the slurry zone of the reactor, thereby forming downwardly extending gas jets of length L in the slurry, the opening of each nozzle being positioned a perpendicular distance D from the surface of the bottom of the reactor, wherein D = 0 75 to 1 5 L
According to a fifth aspect of the invention, there is provided a slurry bubble column reactor comprising a slurry zone arranged to contain in use a volume of slurry comprising a liquid phase in which solid particles are suspended, a gas space above the slurry zone, gas supply apparatus arranged to supply gas to the slurry zone, a gas outlet from the gas space, and a liquid outlet, the gas supply apparatus comprising gas supply and distribution means and a set of gas nozzles, the gas supply and distribution means being arranged to deliver the gas to the set of gas nozzles, the nozzles opening downwards and being arranged in use to inject gas into the slurry zone of the reactor, thereby forming downwardly extending gas jets of length L in the slurry, the gas supply means and gas distribution means being tubular, and the gas supply means being connected to one or more gas supply inlets and also to a plurality of gas distribution means, along which the nozzles are generally evenly arranged
The preferred features of the first aspect of the invention may be equally applicable to the second, third, fourth and fifth aspects
The invention also extends to methods of operating the reactors according to the invention to carry out reactions, to the products of those reactions and to further methods comprising various post-processing operations and to the products of such further methods
Certain terms used in this specification will now be explained in more detail

9
A plume of gas is formed at the nozzle mouth by gas flowing through the nozzle mouth and
into the slurry phase The plume may contain isolated volumes of the liquid phase, particularly as liquid drops from the surrounding liquid phase Within the plume the gas phase is the continuous phase, however The length L is the length of the jet in the dominant direction of the gas flow through the nozzle mouth
Dynamic pressure of the gas This is defined as "The pressure of a fluid resulting from its motion, equal to one half the fluid density times the fluid velocity squared" in Handbook of Chemistry and Physics, 1 e q=0 5rv2, these are exactly the same units as for kinetic energy, which is defined also in Handbook of Chemistry and Physics "The kinetic energy per unit volume of a fluid parcel is thus 0 51rv2, where r is the density and v is the speed of the parcel" Based on the definition, kinetic energy will have the units (kg/m3)*(m2/s2) = kg/m s2
The invention may be carried into practice in various ways, and some embodiments will now be described by way of example, in which
Figure 1 is a top plan view of the gas distributor in the bottom of a reactor vessel, Figure 2 is a cross-section on the line A-A in Figure 1, simplified for reasons of clarity, Figure 3 is a section through a simple nozzle, and Figure 4 is a section through an alternative form of nozzle
The gas distributor 11 is located in the bottom of a reactor 12 It comprises a main gas feed pipe 13, three gas manifolds 14 and beneath the manifold 14, a series of concentric tubular gas distribution rings 20, 21, 22, 23, 24 The rings 20-24 are connected to the manifolds 14 by means of respective gas supply tubes 30, 31, 32, 33, 34 It will be appreciated that while five rings are shown, there could be fewer or more, depending on various factors, such as the dimensions of the reactor and the rings themselves
The bottom of the reactor 12 is curved and in order to maintain a substantially constant spacing between the rings 20-24 and the reactor inside surface, the elevation of the rings 20-

10
24 within the reactor increases in a radially outward direction This is achieved by selecting
appropriate lengths for the supply tubes 30-34
Each of the rings 20-24 is formed with a series of nozzles which are generally equispaced along the ring 20-24, and are also similarly spaced from the nozzles on adjacent rings The nozzles are shown in more detail in Figures 3 and 4
Figure 3 shows a nozzle in the form of a simple hole 40 in a ring 20 Figure 4 shows an alternative nozzle in the form of a hole 52 in a ring 20 covered by a cowl 50 which has an aperture 51 In each case, the hole 40 or the aperture 51 faces downwards, and more specifically, downwards and perpendicularly towards the inner surface of the bottom of the reactor 11
In use, the reactant gas is conveyed to the feed pipe 13 and enters the three manifolds 14, from there it enters the rings 20-24 via the tubes 30-34, and is injected into the slurry in the reactor zone 12 through the nozzles 40 (or 50, 51) In this way, each nozzle produces a downward gas jet into the slurry These jets flush the surface of the reactor 11 to prevent the catalyst settling and keep the catalyst in motion
The parameters of a practical embodiment in accordance with Figures 1, 2 and 3 are as follows
Reactor height 25 m
Reactor diameter 27 m
Reactor pressure 19 5 bar
Reaction temperature 225 degrees C
Feed gas composition
H2 59 mol%
CO 28 mol%
co2 11 mol%
N2 2 mol%

11
Gas velocity 0 18 m/s
Catalyst particle cone 20 wt %
Gas hold-up 0 25
Density, slurry 802 kg/m3
Gas flow (volume) 1 0 m3/s
Total number of orifices 550
Jet length (le L) 12 5 cm
Mean pressure drop,
orifice 0 19 bar
Orifice gas velocity 45 m/s
Orifice diameter 7 5 mm
Mean distance
between orifices 3 75 cm
Min tube diameter 5 5 cm (I D)
Min orifice pressure drop 0 17 bar
Dynamic, pressure 6900 kg/ms
The invention will be further illustrated in the following Examples
Example 1 Gas jet length from gas distributors with downward-pointing nozzles
A 50 cm diameter coldflow reactor operated at room temperature and atmospheric pressure was filled with water Air was fed to the reactor through a gas distributor with 20 downward-pointing nozzles Two different nozzle mouth diameters were tested, 1 9 mm and 2 5 mm The gas flow varied, and the resulting gas jet length was measured
Another reactor, with a diameter of 20 cm, also operated at room temperature, but at elevated pressures, was filled with a hydrocarbon liquid Nitrogen was fed to the reactor through a single downward-pointing nozzle Nozzles with two different nozzle mouth diameters were tested, 5 mm and 10 mm The pressure and the gas flow were varied, and the resulting gas jet length was measured The results are shown in Figure 5 where the measured gas jet lengths are shown as a function of the energy content in the gas, expressed as 0 5pvOr 2, where p is the

12
density of the gas and vor is the gas velocity through the nozzle mouth As can be seen from
Figure 5, there is a clear relationship between the energy content of the gas and the resulting length of the gas jet, which can be used to estimate the length of the gas jet, and thereby determine the necessary distance between the nozzle outlets and the bottom of the reactor
Example 2 Catalyst attrition from gas distributors with downward-pointing nozzles
The 20 cm diameter reactor from Example 1 was filled with a hydrocarbon liquid and 30 wt% alumina particles The reactor pressure was kept at 7 7 bar Nitrogen was fed to the reactor through a gas distributor with 4 downward-pointing nozzles, each with a diameter of 5 mm, and with a nozzle velocity of approximately 70 m/s The attrition of the alumina particles was measured by measuring the particle size distribution of the particles In the Figure 6, the particle size for the 10% fraction of alumina particles is shown as a function of time-on-stream Figure 6 shows that after approximately 150 hours on stream, 10% of the particles have a particle size of 10 µm or smaller Compared with the number of almost 60 µm at the start of the experiment, this clearly shows that the alumina particles suffer from serious attrition with this gas distributor design
In another experiment in the same reactor, with the same reactor conditions, a gas distributor with 4 downward-pointing nozzles with a diameter of 10 mm was used, with a nozzle velocity of approximately 17 m/s Again, the attrition of the alumina particles was measured by measuring the particle size distribution of the particles The results are shown in Figure 6 As can be seen from Figure 6, the particle size for the 10% fraction remains almost unchanged for almost 750 hours, indicating that catalyst attrition is not a problem with this gas distributor design
The experiments show that the nozzle velocity should be low in order to avoid attrition Example 3 Design of a gas distributor with downward-pointing nozzles
A gas distributor is to be designed for a slurry bubble column reactor with a diameter of 2 7 m and a slurry height of 25 m, operated at a pressure of 19 5 bar and a temperature of 225°C, designed for 1763 kmol/h of a synthesis gas consisting of 58 4 H2 %, 27 8 % CO, 11 8 % CO

13
2 and 2% N2 The gas distributor consists of a hemisphencally shaped pipe-grid gas
distributor with downward-pointing nozzles
Since each nozzle covers approximately 1 dm2 of the reactor cross sectional area, approximately 600 nozzles are necessary
The largest axial distance between two nozzles is approximately 25 cm With a slurry density of 800 kg/m3 and a gas void fraction of 0 25, the hydrostatic pressure different between these nozzles becomes 15 mbar Since the nozzle pressure drop should be at least 10 times higher, the minimum nozzle pressure drop becomes 0 15 bar
In Table 1 below, different combinations of nozzle velocities and nozzle diameters are shown, as well as the resulting calculated nozzle pressure drop and estimated gas jet length As can be seen from Table 1, the calculated pressure drop is larger than the minimum pressure drop for all values of the nozzle velocity in the Table In order to keep the attrition of the catalyst as low as possible, as low values as possible should be chosen for the nozzle velocity
Table 1
Nozzle mouth velocity (m/s) 45 50 55 60
Nozzle mouth diameter (m/m) 7,0 6,7 6,3 6,1
Pressure drop (bar) 0,19 0,24 0 30 0,35
Gasjet length (cm) 12,4 14,0 15,9 17,3
Example 4 Nozzle size and attrition
The experiments have shown that for a given flow, 5 mm mouth nozzles gave a catalyst attrition that was too high, while 6 5 mm (and 10 mm) nozzles did not In these experiments, the gas flow was kept constant, so that the nozzle diameter and the nozzle velocity were the only variables The results are shown in Figure 6 and in Figure 7 The results are presented in two different Figures because two different batches of alumina particles with different physical properties were used

14
The attrition resistance of the catalyst is a very important parameter A catalyst with a high attrition resistance can withstand a higher nozzle velocity (and thereby a higher dynamic pressure) than a catalyst with lower attrition resistance It should be noted that the catalysts used in the reported experiments had a relatively high attrition resistance
Table 2
Nozzle diameter (mm) nozzle velocity (m/s) dynamic pressure (kg/m s2)
5 68 19050
6 5 41 6875
In Table 2, the nozzle diameter, nozzle velocity and dynamic pressure in the experiments are shown The table shows that the catalyst used in the experiments can resist nozzle velocities of 40 m/s and a dynamic pressure of 7000 kg/m s2
Having these numbers in mind when looking at Figure 5, where the relationship between jet length and dynamic pressure (kinetic energy) is shown, it means that a slurry bubble column gas distributor should be designed and operated to give numbers on the left side of Figure 5 in order to avoid catalyst attrition It further means that the jet length will be m the order of 10-15 cm, and certainly not above 20 cm (Since other catalysts are most unlikely to have a significantly higher attrition resistance, other catalysts will probably now withstand 5 mm nozzles)
A certain minimum gas velocity is necessary, in order to give a minimum pressure drop through the nozzles, in order to avoid axial maldistribution of the gas
Example 5 Design of large scale bubble column
It will now be shown how a gas distributor for a large scale bubble column is designed The design philosophy can be used for any reactor geometries and conditions

15
Reactor design parameters
Reactor height 2 m
Reactor diameter 2 7m
Pressure 19 5 bar
Temperature 225°C
Gas flow 1763kmol/h
Gas density 6 9 kg/m3
The main principle in the design of the gas distributor is that all nozzles should have the same distance to the bottom of the reactor Since the bottom of the reactor not is flat, but has a hemispherical shape, the nozzles will be located at different axial heights To avoid differences in the axial distribution of gas, the nozzle pressure drop, DPor, should be at least an order of magnitude higher than the hydrostatic pressure difference between the nozzles with the largest axial distance This hydrostatic pressure difference is given by the equation
DPor axial = ps| *g*DLaxia]* (1-e)
where DPoraxiai is the hydrostatic pressure difference between the nozzles with the largest axial distance
psi is the slurry density
g is the gravity constant
DLaxiai is the distance between the nozzles with the largest axial distance
e is the gas hold-up
By using typical numbers for the parameters above, psi = 800 kg/m3 and e = 0 25, and choosing a value for DLaxiai = 29 cm, DPOraxiai becomes 17 mbar, and consequently the minimum nozzle pressure drop, DPor mm becomes 17 mbar * 10 = 0,17 bar
A number of nozzles, Nor, equal to 550 is chosen for the reactor with the diameter given above The gas velocity through each nozzle, uor is defined by the following equation
Uor=Cdor*(2*DPOrm.n/Pg)0 5

16
where CdOr is the orifice coefficient, set equal to 0 6 when the Reynolds number, Re, is higher than 3000
pg is the gas density
(The equation above is only valid for conditions with incompressible flow, l e if uor The diameter of each nozzle, dor, can be calculated from the equation
J = p/4*dor2*uor*Nor where J is the volumetric gas flow into the slurry reactor
For a given nozzle velocity, the resulting nozzle pressure drop and nozzle diameter can be calculated In this case a nozzle velocity of 45 m/s was chosen, which resulted in a nozzle diameter of 7 34 mm and a nozzle pressure drop of 0 19 bar
The calculated nozzles pressure drop is higher than the minimum value of 0 17 bar calculated above, indicating that there will be no axial maldistribution of gas
The gas flow through each nozzle results in a dynamic pressure of 6920 kg/m s2, which is below the value of 7000 mentioned above, indicating that catalyst attrition will not be a problem
Based on the relationship between the dynamic pressure and the jet length (Figure 5), the jet length is estimated to be 12 4 cm, which should be the approximate distance between the nozzle outlets and the reactor bottom over the entire reactor cross sectional area
The nozzles must be distributed over the entire reactor cross sectional area In this area, the design uses five rings, evenly radially distributed over the reactor cross sectional area, and with axial differences corresponding to the hemispherical shape of the reactor bottom To

17
avoid radial maldistribution of gas, the nozzle pressure drop, DPor should be sufficiently large
compared to the dynamic pressure in the gas distributor tubes, and the following criterion should be fulfilled
Apipe/SAor>sqrt(10)*Cdor
With Cd or equal to 0 6, this implies that the pipe area should be at least twice the sum of nozzle areas in the pipe The equation above therefore determines a minimum inner tube diameter in the gas distributor tubes

Claims
1 A slurry bubble column reactor comprising a slurry zone arranged to contain in use a
volume of slurry comprising a liquid phase in which solid particles are suspended, a gas
space above the slurry zone, gas supply apparatus arranged to supply gas to the slurry zone, a
gas outlet from the gas space, and a liquid outlet, the gas supply apparatus comprising gas
supply and distribution means and a set of gas nozzles, the gas supply and distribution means
being arranged to deliver the gas to the set of gas nozzles, the nozzles opening downwards
and being arranged in use to inject gas into the slurry zone of the reactor, thereby forming
downwardly extending gas jets of length L in the slurry, the number and the configuration of
the nozzles being selected to provide a distribution of nozzles across a cross section of the
reactor which corresponds to a minimum density of 75 evenly distributed nozzles per m2 the
opening of each nozzle being positioned a perpendicular distance D from the surface of the
bottom of the reactor, wherein D = 0 75 to 1 5 L
2 A reactor as claimed in Claim 1, in which the gas supply and distribution means
comprise a gas supply means and a separate gas distribution means
3 A reactor as claimed in Claim 2, in which the gas supply means and gas distribution
means are tubular
4 A reactor as claimed in Claim 3, in which the tubular gas supply means is connected
to one or more gas supply inlets and also to a plurality of tubular gas distribution means,
along which the nozzles are arranged
5 A reactor as claimed in Claim 3 or Claim 4, in which the cross sectional area of the
gas distribution means is at least twice the sum of the nozzle areas
6 A reactor as claimed in any of Claims 3 to 5, in which the tubular gas supply means
comprises two or more tubular structures extending radially from one gas supply inlet located
centrally with respect to the general geometry of the reactor, and in which the tubular gas
distribution means are mounted generally perpendicular to the respective axes of the tubular

19
structures comprising the gas supply means to which each tubular gas distribution means is
connected
7 A reactor as claimed in any of Claims 3 to 6, in which the tubular gas distribution
means are in the shape of concentric rings or tubular toroids, or sections thereof
8 A reactor as claimed in any of Claims 3 to 6, in which the tubular gas distribution
means are in the shape of curved tubes, the centre line of each such tube lying in a respective
vertical plane
9 A reactor as claimed in any of Claims 3 to 8, in which the gas distribution means
takes the form of a pipe grid which is part spherical in shape
10 A reactor as claimed in any preceding Claim, in which L is from 5 to 20 cm
11 A reactor as claimed in any preceding Claim, in which the diameter of the openings of
the gas nozzles is equal to or greater than 5 mm
12 A reactor as claimed in any preceding Claim, in which the openings of the nozzles are
arranged so that the principal axis of the jets of gas produced has an inclination of 45° or less
to the vertical
13 A reactor as claimed in any preceding Claim, in which the distribution of nozzles with
respect to a horizontal plane is such that it provides at least 75 nozzles in any arbitrarily
situated circular area of 1 m2
14 A reactor as claimed in any preceding Claim, in which the bottom of the reactor has a
curved or part-spherical shape and the gas distribution means generally conforms to this
shape
15 A reactor as claimed in any preceding Claim, in which the bottom of the reactor has a
curved or part-spherical shape and the openings of the nozzles he on a virtual surface which
conforms to this shape

20
16 A reactor as claimed in any preceding Claim, in which the openings of at least 95% of
the nozzles are equidistant from the bottom of the reactor
17 A reactor as claimed in any preceding Claim, in which the openings of the nozzles are
configured to direct the jet of gas perpendicularly towards the surface of the bottom of the
reactor, when the reactor is in use
18 A reactor as claimed in any preceding Claim, in which the nozzles are constituted by
orifices formed through the wall of the distribution means
19 A method of conducting a chemical reaction involving gaseous reactants which
comprises supplying the gaseous reactants to a reactor as claimed in any of Claims 1 to 18 by
way of the gas supply apparatus, in which method, the reactor contains a volume of slurry
comprising a liquid phase and solid catalyst particles, and the catalyst particles are
maintained in suspension in the slurry by rising gas bubbles from the gas supply apparatus
20 A method as claimed in Claim 19, in which the gas flowing through each individual
nozzle exerts a dynamic pressure of less than 15 000 kg/m s2
21 A method as claimed in Claim 19 or 20, in which the hydrostatic pressure difference
between the highest and the lowest located nozzles in the reactor is less than 10 times the
pressure drop across an individual nozzle
22 A method as claimed in any of Claims 19 to 21, in which the length L and the
distance D satisfy the equation D = 0 8 to 1 4L
23 A method as claimed in Claim 22, in which the reaction is a Fischer-Tropsch
synthesis, and in which the reaction temperature is m the range 150 to 300°C, the reaction
temperature is in the range 175 to 250°C, and the reaction pressure is in the range 1 to 100
bar

21
24 A method as claimed in Claim 23, in which the reaction pressure is in the range 10 to
50 bar
25 A slurry bubble column reactor comprising a slurry zone arranged to contain in use a
volume of slurry comprising a liquid phase in which solid particles are suspended, a gas
space above the slurry zone, gas supply apparatus arranged to supply gas to the slurry zone, a
gas outlet from the gas space, and a liquid outlet, the gas supply apparatus comprising gas
supply and distribution means and a set of gas nozzles, the gas supply and distribution means
being arranged to deliver the gas to the set of gas nozzles, the nozzles opening downwards
and being arranged in use to inject gas into the slurry zone of the reactor, thereby forming
downwardly extending gas jets of length L in the slurry, the nozzles being distributed
generally evenly across the cross section of the reactor and being arranged to direct their gas
jets towards the bottom of the reactor, in order to dislodge settling catalyst particles
26 A slurry bubble column reactor comprising a slurry zone arranged to contain in use a
volume of slurry comprising a liquid phase in which solid particles are suspended, a gas
space above the slurry zone, gas supply apparatus arranged to supply gas to the slurry zone, a
gas outlet from the gas space, and a liquid outlet, the gas supply apparatus comprising gas
supply and distribution means and a set of gas nozzles, the gas supply and distribution means
being arranged to deliver the gas to the set of gas nozzles, the nozzles opening downwards
and being arranged in use to inject gas into the slurry zone of the reactor, thereby forming
downwardly extending gas jets of length L in the slurry, the number and the configuration of
the nozzles being selected to provide a distribution of nozzles across a cross section of the
reactor which corresponds to a minimum density of 75 evenly distributed nozzles per m2
27 A slurry bubble column reactor comprising a slurry zone arranged to contain in use a
volume of slurry comprising a liquid phase in which solid particles are suspended, a gas
space above the slurry zone, gas supply apparatus arranged to supply gas to the slurry zone, a
gas outlet from the gas space, and a liquid outlet, the gas supply apparatus comprising gas
supply and distribution means and a set of gas nozzles, the gas supply and distribution means
being arranged to deliver the gas to the set of gas nozzles, the nozzles opening downwards
and being arranged in use to inject gas into the slurry zone of the reactor, thereby forming

22
downwardly extending gas jets of length L in the slurry, the opening of each nozzle being
positioned a perpendicular distance D from the surface of the bottom of the reactor, wherein D = 0 5 to 1 5 L
28 A slurry bubble column reactor comprising a slurry zone arranged to contain in use a
volume of slurry comprising a liquid phase in which solid particles are suspended, a gas
space above the slurry zone, gas supply apparatus arranged to supply gas to the slurry zone, a
gas outlet from the gas space, and a liquid outlet, the gas supply apparatus comprising gas
supply and distribution means and a set of gas nozzles, the gas supply and distribution means
being arranged to deliver the gas to the set of gas nozzles, the nozzles opening downwards
and being arranged in use to inject gas into the slurry zone of the reactor, thereby forming
downwardly extending gas jets of length L in the slurry, the gas supply means and gas
distribution means being tubular, and the gas supply means being connected to one or more
gas supply inlets and also to a plurality of gas distribution means, along which the nozzles are
generally evenly arranged
29 A slurry bubble column reactor and a method of conducting a chemical reaction
involving gaseous reactants, substantially as herein described with reference to the foregoing
examples and accompanying drawings

Dated this 5th day of October, 2006
A slurry bubble column reactor comprising a slurry zone arranged to contain in use a volume of slurry comprising a liquid phase in which solid particles are suspended, a gas space above the slurry zone, gas supply apparatus (11) arranged to supply gas to the slurry zone, a gas outlet from the gas space, and a liquid outlet The gas supply apparatus (11) comprises a gas supply pipe (13), gas manifolds (14) tubular distribution rings (20-24) and a set of gas nozzles (40) The nozzles (40) open downwards and are arranged in use to inject gas into the slurry zone of the reactor (11), thereby forming downwardly extending gas jets of length L in the slurry The nozzles (40) are distributed generally evenly across the cross section of the reactor (11) and are arranged to direct their gas jets towards the bottom of the reactor (11), in order to dislodge settling catalyst particles.

Documents:

02901-kolnp-2006 abstract.pdf

02901-kolnp-2006 claims.pdf

02901-kolnp-2006 correspondence others.pdf

02901-kolnp-2006 description(complete).pdf

02901-kolnp-2006 drawings.pdf

02901-kolnp-2006 form-1.pdf

02901-kolnp-2006 form-2.pdf

02901-kolnp-2006 form-3.pdf

02901-kolnp-2006 form-5.pdf

02901-kolnp-2006 international publication.pdf

02901-kolnp-2006 international search authority report.pdf

02901-kolnp-2006 priority document.pdf

02901-kolnp-2006-correspondence others-1.1.pdf

02901-kolnp-2006-form-1-1.1.pdf

02901-kolnp-2006-form-26.pdf

02901-kolnp-2006-form-3-1.1.pdf

2901-KOLNP-2006-ABSTRACT 1.1.pdf

2901-KOLNP-2006-ABSTRACT 1.2.pdf

2901-KOLNP-2006-AMANDED CLAIMS.pdf

2901-KOLNP-2006-CANCELLED PAGES.pdf

2901-KOLNP-2006-CLAIMS 1.1.pdf

2901-KOLNP-2006-CORRESPONDENCE.pdf

2901-KOLNP-2006-DESCRIPTION (COMPLETE) 1.1.pdf

2901-KOLNP-2006-DESCRIPTION (COMPLETE) 1.2.pdf

2901-kolnp-2006-form 1-1.3.pdf

2901-KOLNP-2006-FORM 1.1.1.pdf

2901-KOLNP-2006-FORM 1.2.pdf

2901-KOLNP-2006-FORM 13.pdf

2901-KOLNP-2006-FORM 2.1.1.pdf

2901-KOLNP-2006-FORM 2.2.pdf

2901-KOLNP-2006-FORM 27.pdf

2901-KOLNP-2006-FORM 3.1.1.pdf

2901-KOLNP-2006-FORM-27-1.pdf

2901-KOLNP-2006-OTHERS 1.2.pdf

2901-KOLNP-2006-OTHERS.pdf

2901-KOLNP-2006-REPLY TO EXAMINATION REPORT 1.2.pdf

2901-KOLNP-2006-REPLY TO EXAMINATION REPORT.pdf

abstract-02901-kolnp-2006.jpg


Patent Number 245000
Indian Patent Application Number 2901/KOLNP/2006
PG Journal Number 53/2010
Publication Date 31-Dec-2010
Grant Date 28-Dec-2010
Date of Filing 10-Oct-2006
Name of Patentee SATOIL ASA
Applicant Address N-4035 Stavanger
Inventors:
# Inventor's Name Inventor's Address
1 Trond MYRSTAD Sildrapevien 28 G,N-7048 Trondheim
2 Pal,SORAKER Ole Nordggards vie 76,N-7049 Trondheim
3 Petter, LIAN Alv Sciefloesvie 8,N -7058 Jakobsli
4 Hallvard,SVENDSEN Frydenbergveien 20D,N-7035 Trondheim
5 Arene,GRISLINGAS Ole Nordgaardvie 36B,N-7049 Trondheim
PCT International Classification Number B01J8/18; B01J8/22
PCT International Application Number PCT/GB2005/001104
PCT International Filing date 2005-03-23
PCT Conventions:
# PCT Application Number Date of Convention Priority Country
1 0407621.2 2004-04-02 Norway